Hide panel
Ecosystem type
Select
Thank you! Your submission has been received!
Oops! Something went wrong while submitting the form.
Land-use challenge
Select
Thank you! Your submission has been received!
Oops! Something went wrong while submitting the form.
NbS approach
Select
Thank you! Your submission has been received!
Oops! Something went wrong while submitting the form.
Clear allAbout the libraryGuide
Freshwater bodies and Rivers
Extreme climate events
Wetland and water management

Landowner-Led Stream and Wetland Restoration for Water Quality and Drought Resilience in the Tullstorp Catchment, Sweden

Location

Tullstorp Stream catchment, Scania/Skåne, Sweden

Status

Project ended

Scale

Landscape level

In a highly productive agricultural landscape where wetlands had been drained and the stream channelised, landowners organised to restore the Tullstorp Stream and rebuild wetland functions across the wider catchment. The project combined river re-meandering, buffer zones, flood storage areas and wetland creation to improve ecological status and cut nutrient leakage to the Baltic Sea. A follow-on initiative (Tullstorp 2.0) expanded the approach to address drought and flooding risks by storing excess water in multifunctional wetlands and reusing it through recirculating irrigation and adapted drainage.

The Tullstorp Stream is a 30 km watercourse in southern Sweden, draining a catchment that is about 85% agricultural land with very high yields and national importance for food production. Historical land-use change reduced wet areas as farmland expanded, and the stream was channelised in the early 1900s as part of agricultural development. By 2009, the stream’s ecological condition was assessed as “bad”, creating a need for substantial restoration to move towards “good” ecological status under the EU Water Framework Directive. Recent extreme weather (very wet 2017 and very dry 2018) highlighted growing climate-related water management challenges for farmers, including drought impacts, drainage pressures, and uncertainty around water withdrawal for irrigation.

Highlights

  • Landowners formed and ran the project through the Tullstorp Stream Economic Association, reducing administrative burdens via an employed project manager and using voluntary participation under a shared land-contract model.
  • Restoration was planned at catchment scale (6,300 ha) and implemented through a phased approach (three 5–10 km phases), including a 2 km “stretch of display” to demonstrate benefits early and build buy-in.
  • By 2019, 39 wetlands had been constructed and 169 ha of wetlands created, alongside 10 km of stream restoration (with monitoring for flow, water quality, benthic communities, and annual fish surveys at 5–7 stations).
  • Reported water-quality outcomes include a 30% reduction in nitrogen content and a 50% reduction in phosphorus content in the river.
  • A second-generation project (2019–2025) is piloting multifunctional water reservoirs linked to recirculating irrigation and customised drainage, including pilots restoring former sugar mill ponds and building a new reservoir fed by drainage systems.

Timeline

  • 2007: Proposals for wetlands at Beddinge Meadows.
  • 2008 March: Idea to restore Tullstorp Stream emerged.
  • 2008 April: Landowner anchoring and presentations to the Municipality and County Administrative Board.
  • 2008 August: Habitat mapping, wetland inventory, and planning/prioritisation report.
  • 2008 September: Flower and bird mapping at Beddinge Meadows; presentation to the Agency for Marine and Water Management; interest association board established.
  • 2008 November - December: Planning of “stretch for display” and information meetings.
  • 2009 January: Project plan and budget finalised; planning and meetings.
  • 2009 February: Tullstorp Stream Economic Association established.
  • 2009 - 2019: 39 wetlands and 10 km river restoration completed; project ongoing with 3–4 years of restoration work remaining.
  • 2019: Tullstorp Stream 2.0 initiated with a pre-study; pilots underway.
  • 2019 - 2025: Tullstorp Stream 2.0 project duration

About the intervention

The first-generation intervention (from 2009) restored the Tullstorp Stream and rebuilt wetland functions across a 6,300 ha agricultural catchment through phased river works and distributed wetland creation. Physical measures included re-meandering and reshaping the river channel, establishing buffer zones and flood zones, and constructing wetlands that intercept drainage water before it reaches the stream. The second-generation intervention (from 2019) extends this approach to climate resilience by creating multifunctional water reservoirs designed to store excess water during wet periods and supply it during drought through recirculating irrigation and adapted drainage systems. Pilot schemes include restoring existing ponds and building new reservoirs connected to drainage and stormwater inputs, with seasonal pumping from the stream when water levels are high.

Intervention details

The project was organised and operated by the Tullstorp Stream Economic Association, an association of landowners and other catchment stakeholders established in February 2009, with a seven-member board and an employed project manager responsible for administration to reduce the workload for participating landowners. The project used a defined engagement approach (“the Tullstorp method”), starting with detailed information and anchoring among landowners, relying on voluntary participation, patience and a bottom-up approach, and demonstrating success early via a 2 km “stretch of display” near Jordberga. To enable implementation and long-term management, the association secured land contracts for restoration and future management activities; landowners retained ownership and could continue land use as long as it did not conflict with the contract’s intent. For the river works, the stream was divided into three phases of approximately 5–10 km each, with objectives to create varied channel depth, flatten banks, and restore a more meandering planform. Additional in-channel and riparian measures included establishing buffer zones along the stream, creating flood zones in suitable areas, and constructing small wetlands that collect drainage water before it enters the stream, aiming to reduce nutrient leaching from farmland and mitigate flooding and erosion. By 2019, 10 km of stream had been restored and 39 wetlands constructed, totalling 169 ha of wetland area; a further phase was planned to restore around 5 km over the next two years (as stated in the project material). Wetland planning was guided by an inventory identifying 50 potential sites; wetlands were implemented where feasible and where landowners opted in, with stated multiple functions including nutrient retention, flood attenuation, biodiversity support, erosion reduction, and recreation value. A monitoring programme is ongoing to assess impacts, including flow, water quality and zoo-benthos at a sampling site in the lower project area, plus annual fish surveys at five to seven stations. In 2019, landowners initiated Tullstorp Stream 2.0 to address climate-related extremes by combining three components into a circular water system: multifunctional water reservoirs, recirculating irrigation, and customised drainage. In this concept, reservoirs store surface water and nutrients and supply irrigation during water scarcity; recirculating irrigation aims to minimise energy and water use while returning as much stored water and nutrients as possible to crops; customised drainage aims to retain and use rainfall and recycled water/nutrients according to field conditions. Two pilots were described: restoration of former sugar mill ponds fed by drainage water, stormwater and water from the stream, and a newly constructed reservoir fed by drainage water; one description also specifies a plan for about 12 ha of multifunctional wetlands within a 250 ha catchment (150 ha arable land) and pumping from the stream to reservoirs in winter and spring when stream levels are high. The project also supports transfer to other areas by assisting landowners in the Ståstorp Stream catchment to apply the Tullstorp method.

Key stakeholders

  • Tullstorp Stream Economic Association (TSEA)
  • Landowners in the catchment (45 signatories in first phase)
  • Municipality and County Administrative Board of Skåne
  • WWF, LOVA, Region Skåne
  • Naturvårdsingenjörerna AB

Financial metrics

Funding sources

  • National and international funds distributed by the state (covers close to 100% of project costs)
  • Pre-study Tullstorpsån 2.0 financed by WWF, LOVA and Region Skåne

Budget

  • Total cost for the first project: Around 60 million SEK (~€6.0 million)
  • Costs for Tullstorp 2.0: Pre-study cost 0.5 million SEK; pilot-project cost about 10 million SEK (about €1 million)

Outcomes

Environmental

  • Nutrient reduction from Tullstorpsån 1.0: nitrogen ↓30%; phosphorus ↓50%.
  • 39 wetlands constructed by 2019, creating 169 ha of wetland area within the catchment.
  • 10 km of stream restored by 2019.
  • Stream ecological condition improved from “bad” (in 2009) to “moderate” (after restoration progress), with a stated goal of achieving “good” ecological status.
  • Tullstorpsån 2.0 planned: approximately 12 ha multifunctional wetlands, with water pumped from the stream to reservoirs in winter and spring when stream levels are high.

Social

  • 45 landowners in first phase signed land contracts enabling works and future management.
  • Governance via TSEA reduces administrative burden on farmers.
  • Improved recreation and wildlife appreciation; method transfer to Ståstorp Stream with TSEA support.

Economic

  • Project funding covers close to 100% of costs; landowners receive compensation for restored stream areas and wetland subsidies.
  • Design principle to avoid reducing farm economic/agronomic yields.
  • Expected economic co-benefits from Tullstorpsån 2.0 include improved cultivation and higher yields through irrigation in dry periods.

Risks and considerations

  • The project’s completion depends on continued state-distributed funding; lack of funding is identified as a major threat.
  • Delivery timescales are long and can reduce participant patience and dampen initial enthusiasm; there is also a risk of “pioneer” fatigue among early drivers.
  • Misunderstanding of restoration objectives and political factors are identified risks.
  • Formal approvals are required: river restoration measures and construction of multifunctional wetlands require approval by the Swedish Environmental Court.
  • The current Swedish funding system is described as supporting river and wetland restoration but not (yet) irrigation and drainage projects, creating a barrier for full-scale rollout of Tullstorp 2.0

Lessons learned

  • Governance & policy: Formal cooperation arrangements across landowners (e.g., a land contract that grants implementation and future management rights while landowners retain ownership) enables catchment-scale delivery; policy and funding frameworks must expand beyond ecology to include irrigation and drainage for climate resilience. Funding & economics: Near-full public funding and farmer compensation underpin participation; future support schemes should reward multi-benefit outcomes (storage/irrigation/drainage). Stakeholder engagement: Early demonstration site showed what restoration looks like in practice and builded confidence among the landowners. Design & operations: Drought periods require larger, deeper reservoirs to ensure water availability.

Sources

For Reference

  1. Tullstorp Stream Project, 2025.
  2. EEA, 2021. Nature-based Solutions in Europe: Policy, knowledge and practice for climate change adaptation and disaster risk reduction

Related EU projects

Information not available yet.